Settings — hours, rain, net arrival, casa order
Net on the farm
Details — overall dates, rates, chart, task by task, scope, method
Rates used
Person-hours / 100 m = the hours of all the people together to finish 100 m of row (a crew of 3 on 1.62 person-hours takes 1.62 ÷ 3 = 32 min). Min crew = the fewest people the task can run with (Lior). Cap = the most people the forecast puts on one task in one casa at once — our assumption (2× the minimum, or the plan’s biggest crew for the task), not Lior’s. Measured = median of Lior’s reports; confirmed = checked against the field on 29 Sep; estimate = derived, not measured directly. Metres a day use the hours-per-day setting above.
When each task would run, casa by casa
Each bar runs from the day a crew would start that task in that casa to the day it finishes. Hover for the numbers.
Task by task
Scope — tap a cell to take it out
Metres still to do per task and casa. Take out what is not going to be done (e.g. casa 7 A–B nets are not in net order MO 2822).